April 29, 1981 City of Detroit/General Motors Corporation; Central Industrial Park Project 14.6

The definition of "begin actual construction" does not cover demolition activities. Site preparation activities do not, in and of themselves trigger PSD review. The definition of "construction" for PSD includes the term demolition, but this is included in order for emission reductions from demolition to be added to the available increment.