November 26, 1980 Request for Extension on PSD Permit for Indianapolis Power and Light Company 11.2
A source which was issued a PSD permit may be granted an extension on the commencement of construction date based on a decrease in consumer demand depending on the circumstance. Although policy is still being formulated the following evaluating steps should be taken:- Assume company projections are reasonable.
- Coordinate with the State where source is
locating.
- Publish Federal register notice on
proposed extension and solicit comments.
- For phases projects, alert source that an extension, if granted will apply to the first phase.