March 11, 1980 PSD Regulations Require a Source 10.15
A major source if construction commenced after March 19, 1979, would not be subject to PSD review only if:- All final Federal, State, and local preconstruction permits were obtained
before March 1, 1978.
- Construction commenced before March 19, 1979, and
- Did not discontinue construction for a period of 18 months or more
and construction is (was) completed within a reasonable time.
Notebook Entries: 1.10