March 11, 1980 PSD Regulations Require a Source 10.15

A major source if construction commenced after March 19, 1979, would not be subject to PSD review only if:
  1. All final Federal, State, and local preconstruction permits were obtained before March 1, 1978.

  2. Construction commenced before March 19, 1979, and

  3. Did not discontinue construction for a period of 18 months or more and construction is (was) completed within a reasonable time.