Weyerhaeuser Company
Minutes to Meetings Held to Develop Final Project Agreement
Continuous Improvement Review
of
Weyerhaeuser Company's Project XL Agreement
March 12, 1997
Meeting Objective: Signatories review Weyerhaeuser's
Project XL - EPA development and finalization "decision processes"
to document well dones and areas
for improvement.
Key Questions:
How do we improve the XL process?
1.What key decisions did signatories (individually
or as a group) make that are reapplicable to future XL projects?
2.What barriers (perceived and real) where
encountered?
3.What alignment and communications processes
worked well or did not work at all?
4.What customer (internal, stakeholder,
other) feedback has been received since the finalization of the FPA?
5.How do we implement our learnings?
AGENDA
1300
Review Meeting Objective and CIP
Russell
1305
Group Finalize "Key Questions"
Russell
1320
Round Table Discussion of "Key Questions"
Russell
1430
Develop CIP Implementation Plan - PDCA
Russell & Stan
1450
Next Steps
Russell & Stan
1500
Close