DOD: Elmendorf Air Force Base
ENVEST Timeline
PROJECTED ENVVEST TIMELINE
03/09/99 Public Presentation 03/23/99 EPA Completes Transition Policy Applicability and SIC Breakout Determinations 04/15/99 ADEC Issues Completeness Determination on Owner Requested Limits (ORLs) and Title 5 Operating Permit Application 04/22/99 Preliminary Three Party Consensus on Final Project Agreement (FPA) 04/26/99 FPA Published in Federal Register for Public Comment 05/26/99 Three Parties Begin Response to FPA Comments 06/15/99 ADEC Issues HAPs Permit Based on ORLs 06/25/99 FPA Signing Ceremony 12/99 Draft Title 5 Permit Issued d