Oregon
PROJECT SUMMARY INFORMATION PAGE
Project Title & Location
Multi-Media Permit for Sediment Re-Handling
Oregon
Applicant State Agency
Oregon Department of Environmental Quality
Project Contact
Keith Johnson
Oregon Department of Environmental Quality
811 SW 6th Avenue
Portland, OR 97204
(T) 503.229.6431
(F) 503.229.6954
Johnson.keith@deq.state.or.us
In Cooperation with Another Federal Program?
No
Federal Regulatory Flexibility Required?
None
Project Support from Agency Director?
Affirmed
Summary Budget Information
[REDACTED BY US EPA]
PRE-PROPOSAL NARRATIVE
Introduction
The management of dredged sediment is a growing challenge, from both
a regulatory and environmental perspective. Sediment contaminated at levels
too high to allow for unconfined in-water disposal must be either be placed
in a confined in-water disposal facility or handled upland. Both approaches
can prove costly, impose undue regulatory burdens, and be restrictive
to beneficial reuse. A sediment re-handling facility can take sediment
not suitable for in-water disposal, manage it in a treatment cell and
effectively separate the return water from the sediment. The de-watered
sediment can then be analytically screened for a variety of reuse options
(wetlands, clean fill, industrial fill) depending on the "quality" of
the dewatered sediment. Establishing a sediment re-handling facility is
relatively new concept that may prove to be both more environmentally
sustainable (allowing for beneficial reuse) and cost effective than traditional
management mechanisms. There are currently disincentives to this approach
because of the complex regulatory oversight by both Federal and State
agencies. Currently, the only oversight option for "low risk" dewatered
sediments is to use a resource intensive solid waste exemption process.
The goal of this proposal is to develop a multi-media permit for sediment re-handling facilities (whether municipal or private) that: (1) Provides for quicker environmental decision making so sediment can be removed more rapidly from the aquatic environment, (2) Provides clear guidance on when and by what methods de-watered sediment will be evaluated for a variety of beneficial uses, (3) Provides one permit for the management of sediment (incorporates both WQ and SW issues), (4) Is self-implementing for the regulated community (will reference risk-based standards for proper re-use), and (5) Provides a level of oversight and environmental protection appropriate for low risk dewatered sediments, thus allowing limited State resources to focus on high priority contaminated sediment issues.
Funding of this proposal will allow DEQ to develop a streamlined approach to sediment management in upland environments. Through analysis of the chemical and physical characteristics of de-watered sediment, we hope to enable quicker determinations regarding the ultimate disposition of sediment (clean fill, beneficial reuse, disposal). Through more careful analysis and management, sediment can be moved more quickly from the aquatic environment into a re-handling facility for appropriate management.
Project Schedule and Timeframe
This project will take approximately two years and will start approximately
January 1, 2003. The first six months of the project would build on existing
work by expanding the discussion with those benefiting from and being
affected by the multi-media permit. This would be done through a series
of meetings and other contacts that would further define and delineate
the scope the permit. From those discussions a permit outline would be
developed. The next year of the project would be the development of a
boilerplate permit and associated guidance for issuance and implementation.
It is anticipated that at least one Pilot permit would be issued. During
last 6 months of the project, an outreach plan will be implemented that
promotes the use and awareness of the permit. In addition, a follow-up
survey will capture the utility of the permit by those using it. A final
report will be written that includes a Web-based description of the multi-media
permit, example permitted projects, and beneficial uses of this approach.
Program Criteria
Target Priority Environmental Areas
This project would improve water quality through quicker decision making
concerning the removal of contaminated sediment. Deciding whether sediment
that requires dredging but needs to be managed in an upland setting is
not yet a straightforward process. The lack of clear, consistent, and
efficient sediment handling practices can result in contaminated sediment
remaining in the aquatic environment longer periods of time, increasing
the exposure of the aquatic environment to the contamination. In addition
to meeting EPA's and DEQ's priority of improved water quality, this project
is also in accord with DEQ's strategic goal of toxics risk reduction,
by implementation of integrated and streamlined approaches to contaminated
sediment management. DEQ recognizes that sediment contamination is an
area of growing concern and is actively pursuing recommendations regarding
redefining clean fill and adopting HWIR for contaminated sediment. A key
recommendation was to explore a multi-media permit for sediment re-handling
facilities. This multi-media process would coordinate components of the
Hazardous Waste, Solid Waste and Water Quality programs at DEQ to expedite
the disposition and ultimate reuse of dredged sediments. However, DEQ
has not been able to implement this recommendation due to resource limitations.
Use of Incentives as a Tool
DEQ proposes to (1) establish a multi-media permit for sediment re-handling
facilities, (2) provide a single point of contact (by DEQ region) for
such multi-media permits, (3) allow self-certification of beneficial reuse
options for de-watered sediment, (4) expedite sediment handling and reuse
permitting, and (5) develop clear, self-implementing guidance. The goal
of these activities is to provide incentives for the following activities:
- the reduction of threats posed by contaminated sediment to the aquatic environment, as a result of increased sediment management events due to clearer process,
- the beneficial reuse of such sediment, and
- enhanced economic activity due to fewer restrictions on maintenance and navigation dredging projects, and better way for entities to estimate project costs and completion times.
Transferring Innovation
Sediment management is a national issue. Various states and EPA regions
are approaching such management in multiple ways. Streamlined sediment
management will be broadly applicable and provide other jurisdictions
more options for better material management and reuse. By integrating
the regulatory considerations of various DEQ programs into a multi-media
permit, we will be encouraging cross-program partnership, and more efficient
use of resources. DEQ has established a cross-program section, which is
tasked to come up with this sort of "next generation" solution to the
Agency's pressing environmental challenges. Streamlining sediment management
will be one of the first undertakings of this section. Lessons learned
from this cross-program approach will be applied to other Agency issues.
Furthermore, this permitting model could easily be expanded and welcomed
by other states confronted with this growing problem.
Guaranteeing Measures and Accountability
The desired short-term goals are: (1) developing a multi-media permit,
(2) streamlining the permitting process, and (3) encouraging the beneficial
reuse of dewatered sediments. A longer term goal is development of a guide
for sediment handling that would identify likely reuse options for dewatered
sediments given the bulk chemistry of the in-water sediments. Indicators
to measure progress toward these goals include, but are not limited to:
- Have we developed a multi-media permit for sediment re-handling?
- Has the permit streamlined sediment management?
- Are navigation and maintenance dredging projects proceeding more efficiently?
- Is more sediment being beneficially reused?
- Reduction of resource needs for re-handling low risk sediments.
Qualitative Selection Factors
Of the seven selection factors listed, this project supports three of
them:
- feasibility - DEQ is confident this project will achieve its stated goals within the proposed budget and timeframe, as it builds on existing recommendations within the Agency
- multi-medial and multi-government - this project will involve Port authorities and possibly the regional government (METRO), and
- institutional readiness - DEQ has already done considerable work internally on this issue and has created a cross-program section to deal specifically with such multi-media issues.
PROPOSAL BUDGET
[REDACTED BY US EPA]