Jump to main content or area navigation.

Contact Us

Region 2

Serving New Jersey, New York, Puerto Rico, US Virgin Islands and Eight Tribal Nations.

Deconstruction Plan for 130 Liberty Street

The Lower Manhattan Development Corporation (LMDC)'s official Web site has all the current information regarding the deconstruction process of the Deutsche Bank/130 Liberty Street Deconstruction. Exit EPA LMDC acquired the Building from Deutsche Bank on August 31, 2004 and is currently planning to clean and deconstruct the building. The proposed Deconstruction Plan submitted for review to the government regulators provides that the 130 Liberty Street building will be deconstructed in two phases. To obtain a copy of an LMDC document reviewed by the regulatory agencies, please contact Michael Haberman at 212-587-9738 or by e-Mail at Mhaberman@renewnyc.com.

Date Document
January 2011 EPA Accepts Proposed Implementation Plan Amendment Request - Work Procedures for the Disposition and Handling of the Three Generator Exhaust Ports on the 1st Floor [PDF 54 KB, 2 pp]
December 2010 EPA Accepts Proposed Implementation Plan Amendment Request - Removal of Non-friable Asbestos Containing Waterproofing within the Building's Floor Slab System on the 3rd Floor [PDF 31 KB, 2 pp]
December 2010 EPA Accepts Proposed Implementation Plan Amendment Request - Work Procedures for the Removal of Remnant Spray-on Fireproofing on Two Beams on the 2nd Floor [PDF 62 KB, 2 pp]
November 2010 EPA accepts Amendment 17 to the Ambient Air Monitoring Program and Amendment 17 to the Quality Assurance Project Plan [PDF 73 KB, 2 pp]
November 2010 EPA Accepts Proposed Implementation Plan Amendment Request - Removal of Non-friable Asbestos Containing Waterproofing within the Building's Floor Slab System on the 3rd and 1st Floors [PDF 59 KB, 2 pp]
October 2010 EPA accepts Amendment 16 to the Ambient Air Monitoring Program and Amendment 16 to the Quality Assurance Project Plan [PDF 62 KB, 2 pp]
September 2010 EPA accepts Amendment 15 to the Ambient Air Monitoring Program and Amendment 15 to the Quality Assurance Project Plan [PDF 374 KB, 11 pp]
June 2010 EPA accepts Amendment 12 to the Ambient Air Monitoring Program and Amendment 12 to the Quality Assurance Project Plan [PDF 70 KB, 2 pp]
June 2010 EPA accepts Amendment 14 to the Ambient Air Monitoring Program and Amendment 14 to the Quality Assurance Project Plan [PDF 60 KB, 2 pp]
May 2010 EPA accepts Amendment 13 to the Ambient Air Monitoring Program and Amendment 13 to the Quality Assurance Project Plan [PDF 63 KB, 2 pp]
April 2010 EPA accepts Amendment 11 to the Ambient Air Monitoring Program [PDF 60 KB, 2 pp]
March 2010 EPA accepts Proposed Implementation Plan Amendment Request – 3rd Floor and 18th Floor Elevator Motors – Exposure of Lifting Eyes, Lifting Points, and Bases & Removal of Non-friable Asbestos Containing Waterproofing within the Buildings Floor Slab System on the 3rd and 1st Floors [PDF 12 KB, 2 page]
March 2010 EPA accepts Proposed Implementation Plan Amendment Request - Work Procedures for the Removal of Remnant Polyethylene Sheeting as Part of Deconstruction [PDF 64 KB, 2 page]
December 2009 EPA accepts LMDC's proposed revision (third amendment request) to the accepted May 14, 2009 130 Liberty Street Contractor's Implementation Plan for Decontamination and Deconstruction [PDF 76 KB, 2 page]
November 2009 EPA accepts LMDC's proposed revision to the accepted May 14, 2009 130 Liberty Street Contractor's Implementation Plan for Decontamination and Deconstruction and proposed revision to the May 13, 2009 Environment, Health and Safety Plan for the 130 Liberty Street Building Abatement and Deconstruction Project [PDF 758 KB, 2 page]
October 2009 EPA accepts Amendment 9 to the Ambient Air Monitoring Program [PDF 52 KB, 2 page]
September 2009 EPA accepts Proposed Implementation Plan Amendment Request - Work Procedures for the Removal of Remnant Polyethylene Sheeting as Part of Deconstruction [PDF 468 KB, 2 page]
September 2009 EPA accepts Proposed Implementation Plan Amendment Request - Work Procedures for the Removal of Non-Friable Asbestos Containing Waterproofing on the First and Third Floors as Part of Deconstruction [PDF 58 KB, 2 page]
August 2009 EPA accepts Proposed Implementation Plan Amendment Request - Removal of Residual Spray-on Fireproofing using Negative Pressure Tent Enclosures – Basement A and 1st Floor [PDF 327 KB, 2 page]
August 2009 EPA accepts Proposed Implementation Plan Amendment Request - Office of Chief Medical Examiner Screening Operations Area: 2nd Floor [PDF 322 KB, 2 page]
July 2009 EPA accepts 2009 Proposed Amendment #8 to the Ambient Air Monitoring Program Plan [PDF 475 KB, 2 page]
June 2009 EPA accepts Proposed Work Procedures for the Cleaning of WTC Dust and Debris from Interstitial Spaces within FCG 2-3, GRG 1 and GRG BAS-A [PDF 453 KB, 2 page]
June 2009 EPA accepts Proposed Modification to the Accepted May 6, 2009 Variance and Amendment to the Deconstruction and Implementation Plan - Removal of Bank of America ATM Machines from 2nd Floor to the 1st Floor [PDF 652 KB, 4 page]
May 2009 EPA accepts Proposed Amendment to the Deconstruction and Implementation Plan: Removal of Bank of America ATM Cassettes from the 2nd Floor ATM Machines [PDF 51 KB, 2 page]
May 2009 EPA accepts Proposed Modification to the April 8, 2008 Implementation Plan Amendment Request for the Removal and Replacement of Existing Structural Shaft Barriers and Polyethylene Shaft Isolation Barriers - Establishment of Gross Removal Grouping 1 (GRG 1) and Fine Cleaning Groupings 3-2 and 1 (FCG 3-2 & FCG 1) [PDF 529 KB, 2 page]
May 2009 EPA accepts Proposed Implementation Plan Amendment - Gross Removal Grouping - Basement A [PDF 49 KB, 2 page]
May 2009 EPA accepts Proposed Implementation Plan Amendment - Water Cleanup in Previously Cleaned Portion of Basement A [PDF 49 KB, 2 page]
March 2009 EPA accepts Proposal to the Accepted Deconstruction Plan Amendment – Cleaning and Clearance of Stairway B - Floors 1 – 19 [PDF 75 KB, 2 page]
March 2009 EPA accepts Proposed Modification to the March 11, 2009 Implementation Plan Amendment: Temporary Electric Shutdown [PDF 68 KB, 2 page]
March 2009 EPA accepts Proposed Implementation Plan Amendment Request: Temporary Electric Shutdown [PDF 11 KB, 2 page]
March 2009 EPA accepts Deconstruction Plan Amendment – Cleaning and Clearance of Stairway B Floors 1 – 19 [PDF 228 KB, 2 page]
February 2009 EPA accepts Proposed Implementation Plan Amendment Request – Exposure of Concealed Standpipe Sections on Floors 15 - 6, 3, 1, Mezzanine and Basement A [PDF 235 KB, 2 page]
February 2009 EPA accepts Proposed Deconstruction Plan Amendment Request – Alternate Abatement Approach – Fireproofing Third Floor [PDF 262 KB, 2 page]
January 2009

EPA accepts Proposed Implementation Plan Amendment Request - Verification of No Residual Fireproofing: Stairway A Enclosure Floors 17-16 [PDF 247 KB, 2 page]

October 2008

EPA accepts Proposed Modification to the December 12, 2007 Accepted Deconstruction and Implementation Plans Amendment for the Removal of Compromised Bay Slabs [PDF 230 KB, 2 page]

February 2008

2008 Proposed Addendum to 2005 Deconstruction Plan and Proposed 2008 Implementation Plan for 130 Liberty Street [PDF 438 KB, 2 page]

November, 2007 Letter to LMDC re: Variance Reopening Requests and Proposed Plan for a Supplemental Fireproofing Investigation [PDF 411 KB, 2 page]
September, 2006 Letter to NYC Department of Buildings indicating acceptance of Revised Contractor Implementation Plan and the Revised Deconstruction Drawings. [PDF 149 KB, 5 page]
September, 2006 Comments on Revised Deconstruction Implementation Plan and Drawings [PDF 227 KB, 15 page]
June, 2006 Proposed Protocol for Exceedance Reporting and Corrective Actions [PDF 307 KB, 2 page]
June, 2006 Amendment Form for Quality Assurance Project Plan for the Ambient Air Monitoring Program [PDF 123 KB, 3 page]
June, 2006 Amendment Form for Ambient Air Monitoring Program Plan [PDF 101 KB, 2 page]
June, 2006 Acceptance of Revised Roof Search / Cleaning Procedures [PDF 134 KB, 1 page]
June, 2006 Comments on the Draft Deconstruction Implementation Plan and Drawings [PDF 298 KB, 27 pages]
May, 2006 Comments on the May 3, 2006 Draft Coin Vault Drawings [PDF 239 KB, 9 pages]
May, 2006 Draft Coin Vault Drawing D-102 [PDF 1.6 MB, 1 pages]
May, 2006 Draft Coin Vault Drawing D-101 [PDF 2 MB, 1 pages]
April, 2006 Letter from EPA to LMDC on Roof Cleanup and Other Activities [PDF 785 KB, 2 pages]
April, 2006 Letter from EPA to LMDC on Phase II Structural Deconstruction Activities [PDF 1.2 MB, 7 pages]
March, 2006 Notification of Exceedances [PDF 269 KB, 2 pages]
March, 2006 Follow-up EPA letter to LMDC regarding Phase II deconstruction plans [PDF 495 KB, 3 pages]
March, 2006 EPA letter to LMDC regarding abatement and demolition [PDF 3.6 MB, 4 pages]
March, 2006 EPA letter to LMDC regarding Phase II deconstruction plans [PDF 729 KB, 3 pages]
November 2005 EPA letter to LMDC regarding correction factor for PM10 and PM2.5 [PDF 65 KB, 2 pages]
September 2005

EPA Accepts LMDC Plan to Deconstruct Former Deutsche Bank Building

July 2005 EPA comments on LMDC's revised draft Deconstruction Plan for 130 Liberty Street [PDF 514 KB, 44 pages]
  • EPA Letter to LMDC (July 26, 2005)
  • EPA comments
  • State of New York Department of Labor Letter to EPA (July 26, 2005)
  • New York State Department of Environmental Conservation (NYSDEC) comments (June 30, 2005)
January 2005

EPA comments on LMDC's draft Phase 1 Deconstruction Plan for 130 Liberty Street [PDF 604 KB, 23 pages]

  • EPA Letter to (Lower Manhattan Development Corporation) LMDC
  • Gilbane Draft Deconstruction Plan (December 10, 2004)
  • New York State Department of Environmental Conservation (NYSDEC) Letter to EPA (January 20, 2005)
  • State of New York Department of Labor Letter to EPA (January 7, 2005)

 

Jump to main content.