An official website of the United States government.

News Releases from Region 04

THURSDAY: EPA to Host Public Meeting About the Start of Cleanup at the CTS Superfund Site in Asheville, N.C.

11/27/2017
Contact Information: 
Davina Marraccini (marraccini.davina@epa.gov)
404-562-8293, 404-562-8400

ATLANTA (November 27, 2017) The U.S. Environmental Protection Agency (EPA) will hold a public meeting this Thursday to share details about the treatment system being installed at the CTS of Asheville, Inc. Superfund Site to clean up contaminants in the groundwater and soil beneath the former CTS plant. Representatives from EPA will answer questions.

What:             Public Meeting for the CTS of Asheville, Inc. Superfund Site

When:            Thursday, November 30, 2017 from 6:30 p.m. to 8:30 p.m.

Where:           Skyland Fire Department, 9 Miller Road in Asheville

Who:              U.S. Environmental Protection Agency (EPA) Region 4

Press Availability – 5:30 to 6:00 p.m.

Representatives of EPA will answer questions. Members of the media should RSVP to marraccini.davina@epa.gov.

Electrical Resistance Heating (ERH) will be used to treat contaminants in the 1.2-acre source area beneath the former CTS plant at 235 Mills Gap Road. These contaminants include trichloroethene (TCE) and light nonaqueous phase liquid (LNAPL) from weathered fuel oil. CTS has contracted with TRS Group, Inc. to install and operate the treatment system, with oversight from EPA.

ERH is a technology that heats the ground to extract and treat hazardous substances. Electricity runs through electrodes, heating the soil and groundwater to vaporize the contaminants. The vapors are captured and removed through extraction wells. Contaminated vapor is then treated above ground before being discharged to the air.

ERH is a technology that heats the ground to extract and treat hazardous substances. Electricity runs through electrodes, heating the soil and groundwater to vaporize the contaminants. The vapors are captured and removed through extraction wells. Contaminated vapor is then treated above ground before being discharged to the air.

Site preparations began in October 2017, and drilling will begin in December 2017. Construction of the treatment system is expected to be completed in May and it will operate through the fall of 2018. The system is expected to extract at least 95 percent of the TCE from approximately 47,250 cubic yards of material, removing an estimated 20,000 pounds of pollutants.

Monitoring will be conducted while the system is operating to protect on-site workers and the surrounding community. Continuous, real-time ambient air monitoring will be conducted during treatment at four fence line locations, and will be set to alarm if exceedances of action levels are detected.

Dust control measures will be implemented during installation of the treatment system. The treatment system will operate 24/7, except during confirmation sampling. During treatment, the CTS Site will continue to not be accessible to the public. There will be 24-hour site security, including personnel, lights and cameras, while the system is operating. The streets and any area outside of the treatment system will be safe to use as normal. People walking down the street will not notice a change in temperature.

The ERH treatment at the CTS Site is required under a March 7, 2017, interim cleanup settlement between EPA and the U.S. Department of Justice with CTS Corporation, Mills Gap Road Associates and Northrop Grumman Systems Corporation. The settlement also requires In-Situ Chemical Oxidation (ISCO) to treat TCE in an approximately 1.9-acre area to the north of the area being treated by ERH. The cleanup plan was expanded to include this second phase in response to public input. A treatability study for the ISCO portion of the cleanup is scheduled to begin January 2018.

The companies will spend an estimated $9 million total on the ERH and ISCO phases of the interim cleanup. The interim cleanup will be followed by a final site-wide cleanup to address any contamination remaining after the ERH and ISCO technologies have had a chance to work, which will take several years. EPA and the potentially responsible parties will complete the Remedial Investigation/Feasibility Study to evaluate options for the final remedy. EPA will then propose the plan to the public for input before selecting the final remedy.

The CTS of Asheville, Inc. Superfund Site was the location of an electronics manufacturing and electroplating facility that operated from 1952 until 1983. Historical use of solvents in the manufacturing of electronic components at the CTS Site contaminated the soil and groundwater with TCE and other volatile organic compounds. TCE has been linked to various illnesses in people, ranging from effects on the central nervous system, liver, kidneys and immune and endocrine systems to certain types of cancer.

More information about the CTS Site: https://www.epa.gov/superfund/cts-millsgap

A copy of the settlement, which is memorialized in a consent decree, is available at:

https://semspub.epa.gov/work/04/11063456.pdf

Connect with EPA Region 4 on Facebook: www.facebook.com/eparegion4   

And on Twitter: @EPASoutheast

# # #