December 10, 2002
4
Statement of Work: Step 2
lData Collection:
–Plant unit to be operated through design range
•Process parameter data gathered at site on plant data historian
•Third party testing company to collect emissions and meteorological data
•Or data provided by existing plant CEMS and Ambient Air Monitoring System
lApplication Development:
–Acquired data from testing to be used to create the scope of the application
–Application to be applied to the Software CEMS
lApplication Exposition:
–End-user review and approval
•Verification of accuracy and completeness
–Implementation of final design
–Completion of interface to local control system